PROJECT 1041:
3002 Darbo Dr
| Submitted by: | R.A. Smith National |
| Project type: | Conditional Use |
| Description: | New McDonald's Restaurant |
| Status: | supplement needed |
Supplementary documents will be accepted.
| Agency | Status | Requirements | Remarks | Checkout Date | Reviewed |
| Zoning | approved | | 1 2 | 6/12/2009 | 6/12/2009 |
| Traffic Engineering | approved | | 1 | 6/8/2009 | 6/10/2009 |
| Fire | approved | | 1 | 6/15/2009 | 6/18/2009 |
| Engineering | supplement needed | 1 | 2 3 4 5 | 6/10/2009 | 6/11/2009 |
| Planning | approved | | 1 2 | 6/12/2009 | 6/12/2009 |
| Lighting | approved | | 1 | 6/11/2009 | 6/12/2009 |
| Urban Design Commission | approved | | 1 | 6/8/2009 | 6/18/2009 |
| Engineering Mapping | supplement needed | 1 | 2 | 6/12/2009 | 6/12/2009 |
| Revision | Submit date |
| original | 3/27/2008 |
| 1 | 6/8/2009 |
Engineering
Supplementary material required:
Need notary signed maintenance agreement by owner for the stormceptor unit. Contact Jeff Benedict for boilerplate and Exhibit A language.
Note:
Supplementary Condition Completed (was Prior to approval of the conditional use application, the owner shall obtain a permit to plug each existing sanitary sewer lateral that serves a building that is proposed for demolition. For each lateral to be plugged the owner shall deposit $1,000 with the City Engineer in two separate checks in the following amounts: (1). $100 non-refundable deposit for the cost of inspection of the plugging by City staff; and (2). $900 for the cost of City crews to perform the plugging. If the owner elects to complete the plugging of a lateral by private contractor and the plugging is inspected and approved by the City Engineer, the $900 fee shall be refunded to the owner.)
Note:
Supplementary Condition Completed (was Fee for erosion control permit: $285.15. Submit to Jeff Benedict payable to City of Madison Treasurer. )
Note:
Supplementary Condition Completed (was Fee for stormwater management permit: $5 per 1000 sf new impervious area (not just added impervious area). Submit to Jeff Benedict payable to City of Madison Treasurer.)
Note:
Supplementary Condition Completed (was The Applicant shall submit prior to sign-off, digital PDF files to the Engineering Division (attention: Jeff Benedict, email: jbenedict@cityofmadison.com). The digital copies shall be to scale, and shall have a scale bar on the plan set.PDF submittals shall contain the following information:a) Building footprintsb) Internal walkway areasc) Internal site parking areasd) Lot lines and right-of-way linese) Street namesf) Stormwater management facilitiesg) Detail drawings associated with Stormwater Management Facilities (including if applicable planting plans)The Applicant shall submit to jbenedict@cityofmadison.com prior to plan sign-off, electronic copies of any Stormwater Management files including:a) SLAMM .DAT filesb) RECARGA filesc) TR-55/HYDROCAD/Etc.d) Sediment loading calculationsIf calculations are done by hand or are not available electronically the hand copies or printed output shall be scanned to a PDF file and provided. )
Top
Engineering Mapping
Supplementary material required:
City Engineering records indicate that an 8" public sanitary sewer main exists, and the civil site plan identifies this public sanitary main and sewer access structure southeast of the existing brick wall dumpster enclosure. City Engineering does not have record of a recorded public sanitary sewer easement, as this sewer was built in circa 1950 while the property was still in the Town of Blooming Grove. Applicant shall provide a copy of a recorded easement, if one in fact exists, most likely conveyed to the Town prior to annexation to the City of Madison. If an easement of records cannot be found, the current owner shall convey an easement to the City prior to plan approval. Please contact Engineering Mapping Eric Pederson (epederson@cityofmadison.com or 608-266-4056) or Office of Real Estate Services Agent Dana Warren (dwarren@cityofmadison.com or 608-267-1992). Refer to Office of Real Estate Services Project No. 8949 and Engineering Project No. 53B2685.
Note:
Supplementary Condition Completed (was The Applicant shall submit, prior to plan sign-off, a digital CAD file (single file) to the Engineering Program Specialist in the Engineering Division (Lori Zenchenko). The digital CAD file shall be to scale and represent final construction. The single CAD file submittal can be either AutoCAD (dwg) Version 2001 or older, MicroStation (dgn) Version J or older, or Universal (dxf) format and contain the only the following data, each on a separate layer name/level number: a) Building Footprints; b) Internal Walkway Areas; c) Internal Site Parking Areas; d) Other Miscellaneous Impervious Areas (i.e. gravel, crushed stone, bituminous/asphalt, concrete, etc.); e) Right-of-Way lines (public and private); f) All Underlying Lot lines or parcel lines if unplatted; g) Lot numbers or the words “unplatted”; h) Lot/Plat dimensions; i) Street names. All other levels (contours, elevations, etc) are not to be included with this file submittal. NOTE: Email file transmissions preferred Lzenchenko@cityofmadison.com . Include the site address in the subject line of this transmittal. Any changes or additions to the location of the building, sidewalks, parking/pavement during construction will require a new CAD file.)
Top
Fire
Note:
Supplementary Condition Completed (was Submit a site plan that clearly identifies the location of all fire lanes. The fire lanes as identified on this plan will not work they are to narrow at places and also do not make the turning radius. You may consider showing the fire lane in different location, call Scott 261-9843 for details. )
Top
Lighting
Note:
Supplementary Condition Completed (was Too much trespass light. Please submit one copy of revised photometric plot with fixture cutsheets.)
Top
Planning
Note:
Supplementary Condition Completed (was The applicant shall submit the floorplans and four-sided archiectural plans for review and approval by the Planning Division and Urban Design Commission staff. These items shall reflect the elevations approved by the UDC and Plan Commission in October/ November 2007 per staff approval.)
Note:
Supplementary Condition Completed (was The site plan for the proposed restaurant generally conforms to the plans approved by the Plan Commission. However, the applicant needs to submit landscaping plans for review.)
Top
Traffic Engineering
Note:
Supplementary Condition Completed (was The Driveway Approach form is already filled out in Traffic Engineering Office and requires only the fee and deposit to be paid as noted prior to site approval. The Driveway Approach Fee $100.00 M.G.O. and Deposit to Insure Conduit $NONE Make Check Payable to the City of Madison Treasurer to be delivered or mailed to Attention John Leach, Traffic Engineering, Madison Municipal Building, Suite 100, 215 Martin Luther King Jr. Blvd., P.O. Box 2986, Madison, Wisconsin 53701-2986. The Driveway Approach form is in Traffic Engineering Office fill out and requires only the fee. Please contact John Leach, City Traffic Engineering at 267-8755 if you have questions regarding the above items:)
Top
Urban Design Commission
Note:
Supplementary Condition Completed (was Need to provide detailed building elevations including references to building materials and color selection)
Top
Zoning
Note:
Street graphics (sign) review/approval is a separate process. A comprehensive street graphics (sign) package shall be approved by the Urban Design Commission prior to applying for street graphics.
Note:
Supplementary Condition Completed (was Submit and obtain approval for the demolition recycling and reuse plan.)
Top