PROJECT 1399:
402 North Lawn Ave #1 & #2
| Submitted by: | Jim Glueck Architects |
| Project type: | Conditional Use |
| Description: | Creation of addition unit to SFR |
| Status: | completed on 7/3/2009 |
Project has been completed.
| Agency | Status | Requirements | Remarks | Checkout Date | Reviewed |
| Zoning | approved | | 1 2 3 | 6/1/2009 | 6/2/2009 |
| Engineering | approved | | 1 | 5/28/2009 | 6/4/2009 |
| Planning | approved | | 1 | 5/29/2009 | 6/3/2009 |
| Engineering Mapping | approved | | 1 2 | 6/4/2009 | 6/5/2009 |
| Parks | approved | | 1 | 5/29/2009 | 6/8/2009 |
Engineering
Note:
Less than 4,000 sf disturbed area, no Erosion Control & Storm Water Management Permit required.
Top
Engineering Mapping
Note:
The existing house address is now 402 North Lawn Avenue #1. The address for the addition is 402 North Lawn Avenue #2.
Note:
Supplementary Condition Completed (was The Applicant shall submit, prior to plan sign-off, a digital CAD file (single file) to the Engineering Program Specialist in the Engineering Division (Lori Zenchenko). The digital CAD file shall be to scale and represent final construction. The single CAD file submittal can be either AutoCAD (dwg) Version 2001 or older, MicroStation (dgn) Version J or older, or Universal (dxf) format and contain the only the following data, each on a separate layer name/level number: a) Building Footprints; b) Internal Walkway Areas; c) Internal Site Parking Areas; d) Other Miscellaneous Impervious Areas (i.e. gravel, crushed stone, bituminous/asphalt, concrete, etc.); e) Right-of-Way lines (public and private); f) All Underlying Lot lines or parcel lines if unplatted; g) Lot numbers or the words “unplatted”; h) Lot/Plat dimensions; i) Street names. All other levels (contours, elevations, etc) are not to be included with this file submittal. NOTE: Email file transmissions preferred Lzenchenko@cityofmadison.com . Include the site address in the subject line of this transmittal. Any changes or additions to the location of the building, sidewalks, parking/pavement during construction will require a new CAD file.)
Top
Parks
Note:
Supplementary Condition Completed (was 1. The developer shall pay park fees for the additional unit, totaling $2,963.49 for park dedication and development fees.)
Top
Planning
Note:
Submitted elevation drawings include front deck and ramp. This feature was shown on the PC approved site plan.
Top
Zoning
Note:
The 2 stall parking reduction has been approved.
Note:
Supplementary Condition Completed (was Correct the Useable Open Space note on sheet 1.)
Note:
Supplementary Condition Completed (was Show the distances between the 2 unit residence and the lot lines.)