PROJECT 1526: 1901 S Park St

Submitted by:GO/A Architects Inc.
Project type:Permitted Use
Description:reconfigure existing parking lot
Status:supplement needed

Supplementary documents will be accepted.

AgencyStatusRequirementsRemarksCheckout DateReviewed
Zoningsupplement needed1 10/5/200910/9/2009
Traffic Engineeringapproved 19/30/200910/1/2009
Fireapproved  10/1/200910/5/2009
Engineeringapproved 1  29/30/200910/1/2009
Urban Design Commissionapproved  10/6/200910/14/2009
Engineering Mappingapproved 110/1/200910/9/2009

RevisionSubmit date
original9/30/2009


Engineering 

Note: Less than 4,000 sf disturbance for landscape work. No EC/SW permit requirements.

Note: Supplementary Condition Completed (was Submit PDF's of plans for Engineering records. Files can be emailed to Tim Troester at ttroester@cityofmadison.com)

Top
Engineering Mapping 

Note: Site plan proposal contains only minimal changes, therefore Engineering Mapping can make manual changes without CAD file.

Top

Traffic Engineering 

Note: Supplementary Condition Completed (was Supplementary Condition Completed (was The Driveway Approach form is already filled out in Traffic Engineering Office and requires only the fee and deposit to be paid as noted prior to site approval. “Permit to Construct Commercial Driveway Approach.” The Driveway Approach Fee $ 100.00 M.G.O. and Deposit to Insure Conduit $ NONE Make Check Payable to the City of Madison Treasurer to be delivered or mailed to Attention John Leach, Traffic Engineering, Madison Municipal Building, Suite 100, 215 Martin Luther King Jr. Blvd., P.O. Box 2986, Madison, Wisconsin 53701-2986. ))

Top

Zoning 

Supplementary material required: Submit details of the model of bike rack to be installed.

Top