PROJECT 1544:
1701 McKenna Blvd
| Submitted by: | Duane Hinz |
| Project type: | Minor Alteration to CU |
| Description: | new tree islands / lot confuiguration |
| Status: | completed on 11/13/2009 |
Project has been completed.
| Agency | Status | Requirements | Remarks | Checkout Date | Reviewed |
| Zoning | approved | | 1 | 10/21/2009 | 10/21/2009 |
| Traffic Engineering | approved | | | 10/16/2009 | 10/16/2009 |
| Fire | approved | | | 10/22/2009 | 10/27/2009 |
| Engineering | approved | | 1 | 10/21/2009 | 10/21/2009 |
| Planning | approved | | | 10/21/2009 | 10/21/2009 |
| Urban Design Commission | approved | | | 10/20/2009 | 10/23/2009 |
| Engineering Mapping | approved | | 1 2 | 10/26/2009 | 10/28/2009 |
Engineering
Note:
Supplementary Condition Completed (was Submit PDF's of the plans for Engineering records. Files can be emailed to Tim Troester at ttroester@cityofmadison.com)
Top
Engineering Mapping
Note:
Supplementary Condition Completed (was The Applicant shall submit, prior to plan sign-off, a digital CAD file (single file) to the Engineering Program Specialist in the Engineering Division (Lori Zenchenko). The digital CAD file shall be to scale and represent final construction. The single CAD file submittal can be either AutoCAD (dwg) Version 2001 or older, MicroStation (dgn) Version J or older, or Universal (dxf) format and contain the only the following data, each on a separate layer name/level number: a) Building Footprints; b) Internal Walkway Areas; c) Internal Site Parking Areas; d) Other Miscellaneous Impervious Areas (i.e. gravel, crushed stone, bituminous/asphalt, concrete, etc.); e) Right-of-Way lines (public and private); f) All Underlying Lot lines or parcel lines if unplatted; g) Lot numbers or the words “unplatted”; h) Lot/Plat dimensions; i) Street names. All other levels (contours, elevations, etc) are not to be included with this file submittal. NOTE: Email file transmissions preferred Lzenchenko@cityofmadison.com . Include the site address in the subject line of this transmittal. Any changes or additions to the location of the building, sidewalks, parking/pavement during construction will require a new CAD file.)
Note:
Supplementary Condition Completed (was "Reply all" to 10/28/2009 email from Eric Pederson Engineering Mapping and include the PDF plan sheets that summarizes the private sanitary sewer lateral location per your televised locate so that we may update our sanitary lateral records for this site. The additional CAD supplement can be included with this email.)
Top
Zoning
Note:
Supplementary Condition Completed (was Plant additional vegetation in the 2 landscape islands in the east parking lot for a minimum of 75% vegetative cover. Vegetative cover can include trees, shrubs, ground cover, and/or grass. Up to 25% of the island surface may be brick pavers, mulch or other non-vegetative cover.)